Project Update- One of our sites in London is coming to life one steel beam at a time!
With steel nearing complete across most zones and decking well underway, works have now officially began on Zones 7 and 9.
The latest progress in key statistics:
- Zones 1 & 2- Steel & decking complete
- Zone 3- 90% steel complete
- Zone 5- Steel complete, decking 90% installed
- Zone 6- Steel complete
- Zone 7- Steel commenced this week
- Zone 8- Steel complete
- Zone 9- Steel commenced this week
Keep an eye out for more updates coming soon