Progress Update: Edinburgh St James Centre

Edinburgh St James Centre

A year has passed since BHC began erecting steelwork and installing metal decking at the Edinburgh St James Centre. 

Since last summer, BHC has erected an astounding 8,800 tonnes of steelwork, equating to approximately 15,000 individual pieces.

In addition to being awarded the structural steelwork packages, BHC has been installing metal decking. A total of 55,144m2 of metal decking has been fitted which is 45% of the total area to be covered with metal decking.