Project Details:

Hot Rolled Steelwork:

1143 tonnes

Cold Formed Steelwork:

18 tonnes

Metal Decking:

14,711 m²

Precast Stairs:

40 lifts

Steel Stairs:

64 lifts

Client:

Gregor Shore Ltd.

Main Contractor:

Gregor Shore Ltd.

Architect:

EMA Architecture & Design

Structural Engineer:

Fairhurst Consulting Structural & Civil Engineers

References:

Scott Currie
(Commercial Manager)
Gregor Shore Ltd.

plot 28 granton structural steelwork project

Plot 28
Granton, Edinburgh

Plot 28 was awarded to BHC Ltd. due to our excellent record on Plot 4, Granton, which was built on-time and on budget.

The project involved the construction of a seven floor residential development with podium level and associated car parking underneath.

There are three buildings involved, two identical buildings (handed) and one U-shaped building.

BHC Ltd. supplied and erected hot rolled steelwork, cold formed purlins, and metal decking along with all necessary safety netting. We also installed the precast stairs and steel stairs.

This project was erected using our own in-house steel erection squads, metal decking squads, mobile cranes and mobile elevated working platforms.

plot 28 granton structural steel project