Project Details:

Hot Rolled Steelwork:

215 tonnes

Cold Formed Steelwork:

20 tonnes

Roof Cladding:

3,072m²

Wall Cladding:

1,955m²

Client:

Lafarge Cement UK

Main Contractor:

BHC Ltd.

Architect:

Lafarge Cement UK

Structural Engineer:

Bingham Yates & Partners

Reference:

Brian McCraw
Lafarge Cement UK

lafarge cement dunbar structural steelwork project

Packaging/Palletiser Warehouse for Lafarge Cement

BHC Ltd. supplied and erected all hot rolled steelwork, cold rolled roof purlins and side/gable rails, single skin roof cladding and rooflights, single skin wall cladding, roller shutter doors, packaging plant access platform steelwork (including open grid flooring and access ladders), together with all necessary safety netting and edge protection.
Foundations, underground drainage and shuttered walls.

The project was completed using our directly employed labour for all trades well within the required programme.