Project Details:

Hot Rolled Steelwork:

847 tonnes

Cold Formed Steelwork:

80 tonnes

Metal Decking:

7928 m²

Edge Protection:

1700 metres

Steel Stairs:

5 No.

Site Duration:

16 weeks

Client:

North Lanarkshire Council

Main Contractor:

Balfour Beatty Construction Ltd.

Architect:

Aedas Architects Ltd.

Structural Engineer:

WSP

References:

George Young
(Project Manager)
Balfour Beatty

Tommy McAteer
(Project Manager)
Balfour Beatty

coatbridge high school structural steelwork project

Coatbridge High School, Coatbridge

Coatbridge High School is a new-build high school to replace the existing school, which was demolished just before BHC site start.

The project involved the construction of a 2/3 storey school with both dual and monopitched roofs and a waveform curved roof to the games hall.

BHC Ltd. supplied and erected hot rolled steelwork and cold formed purlins and side rails for the project. We also supplied and installed metal decking along with all necessary safety netting, and edge protection. In additionally, BHC Ltd. installed the steel stairs supplied by others.

This project was erected using our own in-house steel erection squads, metal decking squads, mobile cranes and mobile elevated working platforms.

coatbridge high school construction project coatbridge high school structural steelwork